On 31 July 2025 excavation of Hyper-Kamiokande's main cavern was completed about 600 m underground near Kamioka, after work on the main cavern began in November 2022 and the dome was finished in October 2023. The cavern, about 69 m in diameter and 94 m high, is among the largest ever excavated underground. Lining of the water tank followed, with photosensor installation planned from 2027 and operations from 2028.

- Date
- 31 July 2025
- Kind of event
- Experiment
- People involved
- Francesca Di Lodovico, Masato Shiozawa
- Experiments
- Hyper-Kamiokande, Kamioka Observatory
The situation before
Super-Kamiokande, a 50,000-tonne water Cherenkov detector operating in the Kamioka mine since 1996, discovered atmospheric neutrino oscillations and has served as the far detector of T2K. To measure CP violation in neutrinos with high significance, search for proton decay at longer lifetimes and catch supernova neutrinos in large numbers, Japanese physicists proposed a successor with a fiducial mass about eight times larger: Hyper-Kamiokande.
The Japanese Diet approved the construction budget in February 2020. The project is led by the University of Tokyo and KEK, with an international collaboration of about 630 researchers from 22 countries by mid-2025. Masato Shiozawa and Francesca Di Lodovico have served as its spokespersons.
What happened
The new site lies under Mount Nijugo in Hida City, Gifu Prefecture, about 8 km south of Super-Kamiokande and about 600 m underground. After access tunnels were completed, excavation of the main cavern began in November 2022. Crews first opened the dome, about 69 m in diameter and 21 m high, which was finished in October 2023. They then excavated downward through the cylindrical part, 73 m high, reinforcing the walls as they went.
The University of Tokyo completed the excavation on 31 July 2025, and KEK announced it on 5 August. The finished cavern is about 94 m high in total and is among the largest rock caverns ever excavated for science. At a site tour in June 2025, shortly before the end of excavation, an official of the science ministry noted that the project was "entering the next stage".
- Dome: about 69 m in diameter, 21 m high (completed October 2023)
- Cylindrical section: about 73 m high
- Total height: about 94 m, at a depth of about 600 m
- Excavation period: November 2022 to 31 July 2025
What followed
With the cavern finished, construction moved to the water tank and its lining, followed by installation of about 20,000 newly developed 50-cm photomultipliers and around 1,000 multi-photosensor modules. Operations are planned to start in 2028. The tank will hold about 260,000 tonnes of ultrapure water.
Meanwhile, the J-PARC accelerator in Tokai has been upgrading its beam power, and a new intermediate water Cherenkov detector is being built about 1 km from the target. Hyper-Kamiokande will compete with DUNE, whose own caverns in South Dakota were finished in February 2024, to establish CP violation in the lepton sector.
Frequently asked questions
When was Hyper-Kamiokande's cavern completed?
Excavation of the main cavern was completed on 31 July 2025, after work began in November 2022.
How big is the Hyper-Kamiokande cavern?
It is about 69 m in diameter and about 94 m high, located roughly 600 m underground.
When will Hyper-Kamiokande start?
Operations are planned for 2028, after the tank and photosensors have been installed.
Original papers
- ProposalK. Abe et al. (Hyper-Kamiokande Proto-Collaboration), Hyper-Kamiokande Design Report, arXiv:1805.04163 (2018)arXiv:1805.04163
Concepts
Last updated: · Editorial standard
Cite this page
Text
Neutrino Atlas (2026). “2025: Hyper-Kamiokande cavern excavation completed”. Retrieved 22 November 2026, from https://neutrino-atlas.com/timeline/2025-hyper-kamiokande-cavern/BibTeX
@misc{neutrinoatlas2026025hyperkamiokandecavern,
title = {2025: Hyper-Kamiokande cavern excavation completed},
author = {{Neutrino Atlas}},
year = {2026},
url = {https://neutrino-atlas.com/timeline/2025-hyper-kamiokande-cavern/},
note = {Accessed 2026-11-22},
language = {english}
}